Scroll down past the map for more details on the projects listed. You can also open the map in a new window(external link).
Update April 2026
Fairfax St, Murchison - UNDERWAY MARCH-AUG
The water main on Fairfax Street needs to be replaced due to its poor condition. This will involve a new pipe in the Parking Bay/berm along Fairfax St. Dates for the works are expected to be 16th March – 7th August 2026. During this time there will be Traffic Management in place, so please follow the signs and directions of staff.
Stage 3 which is about to commence will be from # 92 Fairfax St to #46 Fairfax roughly taking 6 weeks (11th May – 30th June).
Whitby Rd, Wakefield - COMPLETE
The water main on Whitby Road needs to be replaced due to its poor condition. Dates for the works are expected to be 4th November – 18th December 2025. During this time there will be Traffic Management in place, so please follow the signs and directions of staff.
We aim to maintain access to properties during the project. For a few residents, we will contact you directly about access disruptions.
Iwa St, Mapua - COMPLETE
The water main on Iwa Street needs to be replaced due to its poor condition. There will be multiple stages to limit the effect to residents and businesses in the area. Stage 1 we will be installing the new 150mm PVC Watermain on the Western side.
Dates for the stage 1 works are expected to be 22nd September – 24th October 2025.
During this time there will be Traffic Management in place, so please follow the signs and directions of staff.
Stage 2 has a one-way system where you can only enter Iwa Street via Aranui Rd.
Tahi St, Mapua - COMPLETE
The water main on Tahi Street needs to be replaced due to its poor condition. This will involve a new pipe under both sides of the road. Below is a diagram of stage one of the traffic management as we install the pipe from the carpark to Gossi Point along the eastern. We will send out the stage 2 traffic management closer to the time
Dates for the works are expected to be 16th June 2025 – 1st August 2025. During this time there will be Traffic Management in place, so please follow the signs and directions of staff.
Hill Street works COMPLETE
The water main on Hill Street between #101 Queen St and 222 Hill St needs to be replaced due to its and age and poor condition.
Dates for the works are expected to be 3rd to 17th June.
During this time there will be Traffic Management in place, so please follow the signs and directions of staff.
Update March 2025
Upper Queen/Hill Street COMPLETE
The water main on Queen Street between Hill St and #85 needs to be replaced due to its and age and condition. This also involves a pipe under the road and will close the Upper Queen Street section of road during works period. Works dates: 24th February 2025 – 4th April 2025. Once a separate project on Wensley Road works are complete (looking to be in April) we will then move on to Hill Street and have one way/stop go traffic management in place.
Update Jan 2025
Cautley Street - COMPLETE
The water main on Cautley Street between King Street and Giblin Street needs to be replaced due to its age and condition. Works have started and are expected for completion on 21st February 2025. From 4th February to 21st February, road access will be reinstated, with only a shoulder and footpath closed.
About the Project
This project is for a three year programme of reticulation renewals in the Tasman region. These renewals are an ongoing series of works across Tasman designed to renew failing water infrastructure.
First areas of work starting in Māpua and Richmond.
|
Current status |
Delivery |
|
Start Date |
Construction starting end of November as a rolling programme until mid 2027. |
|
End date |
June 2027 |
|
Access |
To be advised in each section. |
|
Contractors |
Ching Contracting |
|
Cost |
$1m for Year 1 |
Contact Us: Email [email protected] for further information reference 1534 Urban Water Reticulation Renewals
This project is the replacement of multiple ageing water mains installed between the 1940s and 1970s throughout Upper Richmond. Area includes Edwards Street, Roeske Street, Wilkes Street, George Street, William Street and Gilbert Street, Richmond.
| Current status | Planning |
| Start Date | TBC |
| End date | 2030 |
| Access | TBC |
| Contractors | TBC |
Contact: Email [email protected] for further information, reference 1507.
This project is to an additional pump-set to service the Richmond South zone independently. This will involve utilising newly installed water mains and a newly constructed reservoir at Hill Street South. Overall this will support the growth in Richmond South.
| Current status | Planning |
| Start Date | 2027 |
| End date | Nov 2027 |
| Access | TBC |
| Contractors | TBC |
Contact: Email [email protected] for further information, reference 1506.
This project is the installation of a new stormwater pipeline within private property on McGlashen Avenue, Richmond. The pipeline will connect to an existing but unused 1350mm diameter stormwater pipe under the Richmond Deviation (SH6). The work programme is be coordinated with the redevelopment of the former bus depot site at 40–44 McGlashen Avenue.
| Current status | Delivery |
| Start Date | October 2025 |
| End date | June 2026 |
| Access | TBC |
| Contractors | Wyatt Construction |
Contact: Email [email protected] for further information, reference 1682.
Paton Reserve is a newly designated recreation reserve set to become a vibrant green space for the local community. Previously a lifestyle block, the 4.5-hectare site will be transformed into a semi-rural park offering a mix of ecological restoration, passive recreation, and community amenities.
The vision for Paton Reserve includes accessible walking trails, picnic areas, orchards, native plantings, and a natural amphitheatre for small-scale events.
Development will be staged over time, guided by community feedback and environmental considerations, with a strong focus on preserving open space, enhancing biodiversity, and fostering partnerships with iwi, schools, and conservation groups.
Paton Reserve is set to become a central green hub for Richmond South, supporting wellbeing, connection, and nature-based experiences for all.
| Current status | Planning |
| Start Date | 2026/27 |
| End date | Autumn 2027 |
| Access | TBC |
| Contractors | TBC |
| Cost | $TBC |
Contact: Email [email protected] for further information, reference 1683.
Consultation on the play space began in May, which included an online survey that drew 455 responses, plus a number of workshops with schools, tamariki, whānau and stakeholders, to hear what aspects were important to our community. We continue to receive great responses – thanks to all who are contributing to the conversation.
The key takeaway so far is the huge need for a regional playspace that caters for our diverse population – not to mention security, accessibility and inclusivity for all ages using the space.
A lot of comments from the schools spoke about the desire to have a playspace that rivals some of those in larger centres, such as the Margaret Mahy Playground in Christchurch.
The survey findings showed a balanced interest in a transitional, natural, traditional, fitness-focused and immersion/themed style of playspace.
Play elements were also evenly spread, with water play, climbing, sliding/swinging and bouncing the most popular to emerge.
We aim to have the project out for tender later this year, start construction circa May 2026 and the first stage open for summer at the end of 2026.
This project is to design and install of a new inclusive and accessible playground. This $1.46 million project is just over 60% funded through the Richmond Reserve Financial Contributions, with the remaining amount shared equally between us and Nelson City Council with Saxton being a shared facility.
| Current status | Planning/Design |
| Start Date | Construction Feb 2025 |
| End date | June 2027 |
| Access | TBC |
| Contractors | TBC |
| Cost | $1.6m |
Contact: Email [email protected] for further information, reference 1609.
Update March 2026
Works begin 30 March along the Easby Park access track and Cropp Place cul-de-sac. Installation will involve trenching, with underground drilling used where possible to reduce disruption.
Working hours are 7:00am–6:00pm, Monday to Friday, with traffic management in place at all times. A road closure will be in effect, with access maintained for residents.
Vehicle access may be temporarily restricted during works, but residents will be notified by text and can contact the Site Manager if urgent access is needed. Access will be restored outside working hours, including overnight and weekends, and pedestrian access will be maintained at all times.
The Easby Park track will be closed to the public during working hours while works are underway in that area, and will reopen once major construction activities are complete.
About the project
A new water pumping station will be constructed at the Selbourne Ave/Cropp Place reserve. The project includes upgraded mains and SCADA integration to improve system reliability and monitoring. These upgrades will help improve the stability and efficiency of the water supply for the area.
|
Current status |
Delivery |
|
Start Date |
30 March 2026 |
|
End date |
June 2026 |
|
Access |
Please see March 2026 update above |
|
Contractors |
Donaldson Civil |
|
Cost |
$323k |
Contact: Email [email protected] for further information, reference 1513.
The Materials Recovery Facility (MRF) at 14 Fittal St, Richmond, is being upgraded to improve recyclables sorting and baling. The project also includes expanding the MRF building to support more efficient operations.
|
Current status |
Planning |
|
Start Date |
Construction Start TBC |
|
End date |
TBC |
|
Access |
TBC |
|
Contractors |
TBC |
|
Cost |
TBC |
Contact: Email [email protected] for more information, reference 1505.
As Richmond South and West grow, we’re upgrading the stormwater network to manage increased runoff, reduce flood risks, and prepare for future climate change impacts. The project focuses on Sections A and B1, which are key channels near Lower Queen Street. These sections, along with the existing road crossing, need upgrades to ensure the whole system works effectively.
The improvements include widening and deepening stormwater channels, upgrading the Lower Queen Street crossing, and ensuring the system meets future climate needs. This work supports the Council’s Urban Stormwater Strategy and will create a more resilient network for Richmond West. Design work began in 2023, and we’ll keep the community updated as the project progresses.
For most recent updates on this project, you can visit Lower Queen Street bridge upgrade | Shape Tasman
| Current status | Construction phase |
| Start Date | May 2025 |
| End date | Sept 2026 |
| Access | Please see Shape Tasman Link above |
| Contractors | Fulton Hogan |
| Cost | $10.09m |
For more information, contact [email protected], reference 1268.
The project involves the upgrade of Section H of the Richmond South Stormwater Upgrade Programme. This includes the installation of a section of watermain and wastewater main between Hill Street South and Cupola Crescent. It also includes the installation of a walkway between Cupola Crescent and Hill Street South. All of this is aimed to support growth in Richmond South.
Update Dec 2025 - Contract 1317 for water and waste water will commence Jan 2026 and a separate contract for the stormwater will follow.
|
Current status |
Delivery/Construction |
|
Start Date |
Jan 2026 |
|
End date |
June 2027 |
|
Access |
To be advised |
|
Contractors |
Fulton Hogan (Water and Waste Water Contract C1317) |
|
Cost |
$1.65m (W and WW C1317) |
Contact: [email protected] for further information, reference 1317.
This project is to build a crossing (bridge) to State Highway 6 to allow connection of stormwater channel to Borck creek. The project will be starting with enabling works to relocate services out of the way and work plans for contaminated land remediation.
|
Current status |
Planning |
|
Start Date |
Construction start: 2029 |
|
End date |
Construction End: 2032 |
|
Access |
TBC |
|
Contractors |
TBC |
|
Cost |
TBC |
Contact: Email [email protected] for further information, reference 1273.
Update May 2026
Work starts the first week of June.
We are renewing the water main along Gladstone Road, from Oxford Street to Three Brothers Corner. This project replaces several existing asbestos cement and cast-iron pipes.
Some of these pipes have been in the ground since 1945, and in the past 10 years, there have been 12 leaks or bursts on the two mains under the road.
Donaldson Civil Construction will be replacing the existing 150mm and 100mm water mains with a single 250mm pipe.
This is part of a $2.5 million project and starts next month – it’s expected to be finished by March 2027.
There should be minimal water disruptions, except when properties are being hooked over to the new line, but there will be plenty of notice before there are any outages.
Traffic and pedestrian management will be in place for the duration of the work, but two lanes of traffic along Gladstone Road will be maintained for most of it.
During stage one of the project, temporary road closures will be needed on Oxford and Waverley Streets. These won’t happen at the same time, and we’ll give residents plenty of notice beforehand.
Vehicle access to some properties will be interrupted at times, but our contractor will work with individual properties and businesses to address any specific needs. Pedestrian access to properties will always be maintained.
Download the Antenno app to keep up to date with any roading and water disruptions.
**
About the project
This project is the replacement and upsizing of water mains pipe from 3 Brothers Corner to the intersection between Gladstone Road and Oxford Street. This pipe replacement will enable increased demands for water services and support growth in Richmond.
| Current status | Planning |
| Start Date | June 2026 |
| End date | Feb 2027 |
| Access | To be advised - see above |
| Contractors | Donaldson Civil Ltd |
| Cost | $2.5m |
Contact: [email protected] for further information, reference 1490.
This project is the upgrade existing culvert to enable Borck Creek to be widened to cater for growth in Richmond South and reduce stormwater flooding.
As of March 2026 - This project is currently On Hold as it is likely to be impacted by the Hope Bypass. Once we have certainty around the design of the Hope Bypass, we can then access our options for the widening of the creek and the replacement of the culvert with a bridge.
| Current status | Design Phase - ON HOLD |
| Start Date | Construction TBC |
| End date | Dec 2028 |
| Access | To be advised |
| Contractors | Not yet appointed |
| Cost | TBC |
Email [email protected] for further information, reference project P1251.
This project is the widening of Borck Creek from SH60 to Reed Andrews Drain (Section C) to cater for growth in Richmond South.
First areas of work starting in Māpua and Richmond.
|
Current status |
Planning |
|
Start Date |
Construction to start 2031 |
|
End date |
Construction to end 2032 |
|
Access |
To be advised |
|
Contractors |
Not yet appointed |
|
Cost |
$TBC |
Contact: Email [email protected] for further information, reference 1252.
This project is the rework of an existing cycle trail bridge to allow for a widened Borck Creek.
Essentially Borck Creek is being widened and Tasman’s Great Taste Trail utilises the vehicle access bridge to #81 Headingly Lane. When Borck creek is widened, the vehicle access will no longer be required, and a longer bridge will be required for cycle access.
It will be built to coincide with the Borck Creek Widening project.
| Current Status | Planning |
| Start date | Construction start date TBC |
| End Date | 2028 - Project timing needs to align with the widening of Borck Creek section A (Headingly Lane to Estuary), |
| Access | To be advised |
| Contractors | Not appointed yet |
| Cost | $TBC |
Contact: Email [email protected] for more information, reference 1556.
Richmond Reticulation Lower Queen Street Trunkmain Upgrade
Lower Queen Street’s trunk main from the intersection with SH6 (Gladstone Road/ Lower Queen St) to just after the intersection with Headingly Lane is a 1960's asbestos pipeline and is nearing the end of its operational life. This project is to upgrade this to modern pipe material and provide more movement and resilience in the ground, all part of moving water where it needs to go in our region.
| Current status |
In design |
| Start Date |
On hold until 2031 |
| End date |
On hold until 2031 |
| Access |
To be advised |
| Contractors |
Not yet appointed |
| Cost |
$TBC |
Contact: Email [email protected] for further information, reference 1449.
Update September 2024
All work is now complete except Section H - See Project Richmond South Section H on this projects page for latest information.
We are installing a new water main from the Richmond water treatment plant to a new reservoir planned for Richmond south. The work is being undertaken in stages in co-operation with private land developers.
This work will improve the resilience of Richmond's water supply and is required to service growth. There are extensive plans for new subdivisions in Richmond west and south in the coming years. This upgrade will ensure we can deliver consistent water supply to all existing and new customers.
There will be major growth in the Richmond South-West area in the next five years.
Click to view a larger version in a new window.
Update May 2026
Richmond’s newest water supply asset is now going through tests before filling over the next few months and coming fully functional in July.
Construction is now complete on a new 2,500 cubic metre low-level water reservoir at Hill Street South near Sunview Heights.
The project is designed to help improve the resilience of the water supply by providing added storage capacity, catering for the growing community in that part of Richmond.
Construction of this 4.9-million-dollar project has been underway for a little over 12 months.
Work is now underway on a 1.3km pipeline that will connect the new reservoir with our water network and the Lower Queen Street treatment plant.
Following on from the pipeline installation work, the stormwater channel (Upper Reed Andrews Creek) will be improved, including a new walkway linking Hill Street and Cupola Crescent.
The full project is likely to be completed in autumn 2027.
Update April 2026
Update June 2025
Work is well underway on Richmond’s newest reservoir, with construction progressing quickly at the Hill Street South site near Sunview Heights.
Once complete, the new 2,500 cubic metre water storage tank will be a key part of our growing water supply network. It will connect to the existing Champion Road reservoir and help ensure a reliable supply for one of Richmond’s fastest-growing areas.
This $4.9 million project, which got underway in February, is all about future-proofing our water infrastructure. The additional storage will improve the network’s resilience and support the needs of our expanding community.
Construction is expected to wrap up early next year, and there’s more to look forward to – plans are in place to develop a shared walking and cycling path alongside the nearby Borck Creek, eventually linking through to Paton Road.
This is just one of the ways we’re investing in essential infrastructure to keep up with growth and make Richmond an even better place to live.
Update January 2025
We have the contractors on board (Fulton Hogan) and their work is set to start February 2025 with an aim to be completed at early 2026. There will be a small increase in the number of vehicles in the area, including heavy trucks and construction vehicles travelling along Hill Street South during construction hours 7am to 6pm. Please remember to take note of all the safety signage and take extra care while using the Hills Street South Road, White Road.
|
Current status |
Construction Phase |
|
Start date |
Construction Feb 2025 |
|
End date |
June 2026 |
|
Access |
There will be a small increase in the number of vehicles in the area, including heavy trucks and construction vehicles travelling along Hill Street South during construction hours. Please remember to take note of all the safety signage and take extra care while using roads in the area. |
|
Contractors |
Fulton Hogan |
|
Cost |
$4.97m |
Richmond is growing a lot faster than previously anticipated. The growth has seen a number of new subdivisions already constructed, and more staged development planned for the Richmond South area, such as Hart Rise and Paton Rise.
More households mean an increased demand for water supply, so we’re planning to build a new concrete water reservoirs (tank) to meet that need.
Artist's impression of new tanks from Hill St South (after approx. ten years planting growth)
The proposed location for the new reservoirs is on a Council owned property at 520 Hill Street South, west of Richmond’s Central Business District (refer map below).
Location of new reservoirs
We looked at a number of possible locations for the reservoir, before choosing this site. As well as having easy access to build and maintain the tanks, an important factor was the ground height, which needed to be at 63m above sea level. That is so the top water level of the new reservoir will be the same level as the existing Richmond Queen Street reservoir, giving us the right conditions to connect the two water supply zones.
520 Hill Street South site location map
A new water main pipe, which is already partly built, will connect the Hill Street South reservoirs to the Richmond water treatment plant. The water main pipe runs along Borck Creek, adjacent the state highway, up Bateup Road Stream, and through the new developments at Hart Rise and Paton Rise.
The reservoir could rise up to 9 metres in height from the base, but that will depend on how far we need to cut in to reach a suitable ground base to build on. Our preferred site option will require the least amount of earthworks to prepare the tank site. It also has the narrowest profile, the smallest silhouette and the smallest site footprint of the four options.
Contact Us: Email [email protected] for further information, reference 1141.
This project is to widen and deepen Channel A of Borck Creek to increase hydraulic capacity through these sections, and consequently to improve the level of service of the network through Richmond West, while addressing the aspirations of the Council’s Urban Stormwater Strategy and the Richmond Catchment Management Plan.
| Current status | Design Phase |
| Start Date | Construction Nov 2027 |
| End date | June 2028 |
| Access | To be advised |
| Contractors | Not yet appointed |
| Cost | $TBC |
Email [email protected] for further information reference 1269.
The project involves installing two new high-lift pumps at the Māpua Water Treatment Plant to replace existing assets and supply treated water to the Māpua-Ruby Bay reservoir and zone customers.
|
Current status |
Planning/ Design |
|
Start Date |
July 2026 |
|
End date |
Sept 2027 |
|
Access |
N/A |
|
Contractors |
Downer (Maintenance Contract) |
|
Cost |
$300,000 |
Contact: Email [email protected] for further information, reference 1518.
This project is the renewal of Korepo Road water main and laterals to fix pressure-related leaks and improve reliability.
The scope of this project is to replace the old water main running along the length of the road, as well as upgrade some of the property service connections (laterals) where required. The construction work will involve 'thrusting' a new pipe (direct drilling) underneath the road, which is a faster method that causes less disruption to residents and traffic.
|
Current status |
Construction Stage |
|
Start Date |
TBC |
|
End date |
June 2027 |
|
Access |
Residents will receive notification prior to works. |
|
Contractors |
Donaldson Civil |
|
Cost |
$392,000 |
Contact: Email [email protected] for further information, reference 1512.
Update March 2026
The first of two projects to improve the Redwood Valley water supply is gaining momentum.
Redwood Valley Rural Water Supply currently takes water from three shallow bores in the Redwood Valley/Waimea plains area, but due to changes in national water quality requirements, a permanent boil water notice was placed on the scheme last year. This was at the direction of the Water Services Authority because the current treatment plants can’t be guaranteed to remove all types of harmful microorganisms.
The project will bring together two water supplies in Redwood Valley into one, with a new Water Treatment Plant to be built on River Road.
Investigations have been done into the best treatment methods, as well as commissioning new bores. We did a survey of the current underground raw water pipe system in 2024 and then drilled two new bores to provide better raw water quality.
A $1.98 million tender has just been awarded for the replacement of the underground piping from the River Road bores to the existing treatment plants at Golden Hills Road and O’Connors Creek.
The consolidation of the two existing water treatment plants into a new one at River Road provides an opportunity to improve treatment to meet water quality requirements and allow the boil water notice to be removed. The two existing treatment plants will be modified into pump stations.
Work on the new five kilometres of underground pipes is expected to begin by July.
This project is to bring together two water supplies in the Redwood Valley into one, with a new Water Treatment Plant build on River Rd. This involves an investigation into the best treatment method, as well as commissioning new bores. We conducted a survey of the current underground raw water pipe system in 2024 and we then drilled two new bores to provide us with a better raw water quality enabling more efficient treatment.
Why are we doing this?
Phase 1: Installation of about 5km of underground piping, part of this in State Highway 60.
Phase 2: Construct Water Treatment Plant
The installation of a new Water Treatment Plant on River Rd, convert the two existing water treatment plants at O’Connors Creek and Golden Hills into Pump Stations, and upgrade the raw (untreated) water pipes from the new bores to the new Water Treatment Plant (WTP). This will begin in 2026 and will take about 16 months.
| Current status |
C1188 - Construction of underground piping underway C1700 - Water Treatment Plant is in Design |
| Start Date | July 2026 for Underground Piping |
| End date | Winter 2027 |
| Access | TBC |
| Contractors | C1188 underground piping - Donaldson Civil |
| Cost | C1188 - $1.98m |
Contact: Email [email protected] for further information, reference 1188.
Pipe alignment indicative only in the map below.
This project aims to secure a new water source for the Dovedale Water Supply Scheme and includes installing a pipeline to the existing Dovedale Water Treatment Plant.
| Current status | Planning |
| Start Date | 2025 |
| End date | 2028 |
| Access | TBC |
| Contractors | TBC |
| Cost | $TBC |
Contact: Email [email protected] for further information, reference 1508.
This contract C1554 includes the roof refurbishment of the Brightwater Hall Roof in 2026 as part of a wider project to undertake building repairs, improve utilisation of space and bring the building up to an appropriate level of service.
| Current status | Delivery |
| Start Date | May 2026 |
| End date | June 2026 |
| Access | TBC |
| Contractors | Scotts Construction |
| Cost | $200k |
Contact: Email [email protected] for further information, reference 1554.
This project renews ageing water reticulation and rider mains in Brightwater on Lord Rutherford, Ellis St, River Terrace. This will integrate with Waimea Plains Project and provide high level of resilience to the Brightwater water supply.
| Current status | Planning |
| Start Date | Works 2028 |
| End date | June 2028 |
| Access | TBC |
| Contractors | TBC |
Contact: Email [email protected] for further information, reference 1516.
We’re upgrading the water and wastewater networks between Edward Street Wakefield and Katania Heights Brightwater. This work is part of a wider programme to improve essential infrastructure in the area.
As part of this project, we will install:
Both pipelines will follow the same route and be installed within a shared trench along Higgins Road.
| Current status | Planning/ Design |
| Start Date | Construction start 2026 |
| End date | June 2028 |
| Access | TBC |
| Contractors | TBC |
Contact: Email [email protected] for further information, reference 1663.
This project involves the design and construction of a new water pump station at the corner of Bird Road and Higgins Road, Brightwater.
| Current status | Delivery/Construction |
| Start Date | Construction start July 2026 |
| End date | June 2027 |
| Access | TBC |
| Contractors | Processflow Ltd |
Contact: Email [email protected] for further information, reference 1659.
This project is to Design and build a new build community hub for the Wakefield community.
You can read more about the project here: Wakefield Community Hub | Shape Tasman
| Current status | Planning |
| Start Date | 2027 |
| End date | 2028 |
| Access | TBC |
| Contractors | TBC |
| Cost | TBC |
For more information, email [email protected], Project ID 1574.
Upgrade reticulation within Wakefield and 88 Valley to allow the majority of the 88 Valley area to be supplied from the Wakefield network via a new line from Gossey Drive North to Totara View Reservoirs. This is all part of improving water supplies to this area. This project is being done in stages.
Stage 1: Construction of pump station in Gossey Drive North and connection of pipeline in Edward St to the new pump station.
| Current status | COMPLETE |
| Start Date | Jan 2025 |
| End date | End of March 2025 |
| Access | COMPLETE |
| Contractors | Downer and Process Flow |
| Cost | $1.5m |
Stage 2: Connection of the pump station with the tanks at Totara View
| Current status | Design |
| Start Date | 2026 |
| End date | 2027 |
| Access | TBC |
| Contractors | TBC |
| Cost | $TBC |
Contact: Email [email protected] reference project 1256.
March 2026 update
There’s been plenty of rain in recent weeks to test us, but progress has been banking up with stage two of the Motueka River Stopbank Refurbishment project.
Our earthworks programme for 2025/2026 has been building on last season’s improvements to the Lower Motueka River stopbank network and Peach Island.
The Lower Motueka River and Brooklyn Stream stopbanks are receiving upgrades across 6.7km, building on the 4.8km initial stage of works.
Refurbishment work will raise the crest of the stopbanks in areas where it is no longer high enough to provide protection from a 1-in-50-year flood event and provide a gravelled 4m crest width for safe access.
It will also address areas where the stopbanks might have weaknesses that could cause them to fail in a large flood event.
Following a great start to works last year with a 720m section refurbishment of the Lower Motueka stopbank, since Christmas we have managed to refurbish a further 900m.
Work around the Peach Island site is all but complete, constructing a broader culvert at the downstream end, allowing water that accumulates to drain faster after flooding.
Between now and the end of April, our staff and contractors will be busy at sites on Motueka River West Bank Road, Anderson Road and College Street.
We are grateful to Kānoa Regional Economic Development & Investment Unit for their co-funding contribution to the project that has enabled this level of refurbishment.
We look forward to the completion of stage two of the project, as well as rolling out the second tranche of co-investment funding announced for Motueka River flood protection upgrades under the Government’s Regional Infrastructure Fund.
December 2025 update
Stage Two of the Motueka River Stopbank Refurbishment project has begun its earthworks programme for 2025/2026, building on last season’s improvements to the Lower Motueka River stopbank network and Peach Island.
The project aims to build resilience and reduce the community’s risk of flooding from the river – the value and necessity of which was made clear after the floods of June/July 2025.
Refurbishment work will raise the crest of the stopbank in areas where it is no longer high enough to provide protection from a 1-in-50-year flood event and provide a gravelled 4m crest width for safe access. It will also address areas where the stopbank might have weaknesses that could cause it to fail in a large flood event.
This year’s activity started well with the first 720m section of the Lower Motueka stopbank nearing completion. In recent days, we also started work on the Peach Island section.
As well as the initial brief of improving maintenance access along the banks, fencing the stopbanks, and ensuring they are appropriately constructed, we will also be constructing a broader culvert at the downstream end of Peach Island, allowing water that accumulates to drain faster after flooding.
We are co-funding this $12.5 million project with a grant of $7.5 million from Kānoa Regional Economic Development & Investment Unit, as part of the Government’s Resilient Infrastructure Fund.
We’ll be carrying out work at several points along the riverbanks – River Road, College Street, Peach Island Road, Motueka West Bank Road, Blue Gum Corner, and Douglas Road. There will be moderate truck movements to and from these sites, but otherwise the public impact will be minimal.
Following a brief break for Christmas, we’ll be back into the swing of things in the New Year, continuing through to April.
October 2025 Update
As we continue to recover and repair from the winter floods, particularly in terms of building river resilience, we have recently had some valuable co-investment funding announced for Motueka River flood protection upgrades under the Government’s Regional Infrastructure Fund.
This is the second tranche of funding from last year’s initial allocation and joins 32 other flood resilience projects around the country which will receive funding.
Tasman’s approved allocation of government funding is $9.48m, and along with Council co-funding of $6.32m, will make for a total project value of $15.8m.
It is estimated that around $2.23 billion of capital value will be protected as a result of the funding.
The funding is intended to construct new and upgrade existing stopbanks and associated flood resilience infrastructure to increase protection to Motueka and the surrounding areas. We had been planning the level of service upgrade for tranche two before the June/July flood events, building on the refurbishment work currently being delivered along the Lower Motueka River and at Peach Island.
However, the effects of the flooding have changed the environment somewhat, as well as how we prioritise our works programme.
Recovery is still a key consideration in our river work. We are working with Kānoa to determine the best use of the tranche two funds, and until we do, we are not able to confirm the specifics of this work. We will continue to keep you updated as decisions are made.
Planned works under the tranche one funding will be taking place in the months ahead.
About the project:
We are progressing the second stage of works of the Lower Motueka River stopbank network, to build resilience and reduce the community’s risk of flooding from the river.
Following the successful completion of Stage One in 2025, funding for the Motueka Stopbanks Refurbishment Project Stage Two was approved by Kānoa Regional Economic Development & Investment Unit, as part of the Government’s Resilient Infrastructure Fund.
We received a grant of $7.5 million from Kānoa, of which $6.6 million will go towards work on the Lower Motueka River stopbank refurbishment, and $900,000 going towards stopbank repairs at Peach Island. We are providing another $5 million in co-funding for a total project budget of $12.5 million.
|
Current status |
Delivery |
|
Start Date |
Works underway as of 30th Oct for Year Two summer works season |
|
End date |
Total works will be May 2028 |
|
Access |
|
|
Contractor (Main) |
Taylors Contracting Ltd |
|
Cost |
See funding information above |
Contact: Email [email protected] for further information, reference project 1572.
We’re sourcing material (soil) from Tasman View Road for the next phase of the Motueka River Stopbank Refurbishment project. At the same time, we’ll be upgrading a section of the road to improve it for future use.
Tasman View Road (Resident Access Only):
We appreciate that this closure will affect recreational users of Tasman View Road, especially for those looking to link with the Great Taste Trail cycleway during the works period.
For your own safety, please follow all signage and instructions from the project team situated at each end of the road.
We will continue to update everyone on progress in the coming weeks through our various channels, including the Council’s Antenno app.
Contact info: Email [email protected] or see Motueka Stopbanks Phase Two (1572) for further information on the project.
We have projects set up to look and improve these existing treatment plants to reduce impact on the environment and meet modern standards.
We are starting with Collingwood, Tākaka and Motueka and improving their Secondary Treatment Systems by investigating the work required and engaging special expertise.
We are looking at nutrient loading, decreasing solids and stormwater flows in all three plants, as well as reducing nitrogen and ammonia that is produced.
|
Current status |
In design |
| Start Date | Jan 2026 |
| End date | Sept 2026 |
| Access | N/A |
| Contractors |
Not yet appointed |
| Cost | $TBC |
Contact: Email [email protected] for further information, reference P1450/1587.
This project is to replace the existing eight plastic storage tanks with one new large reservoir. This upgrade will help future-proof Motueka’s water supply and improve the overall resilience of the system.
|
Current status |
In design |
| Start Date | July 2026 |
| End date | June 2027 |
| Access | TBC |
| Contractors |
Not yet appointed |
| Cost | $TBC |
Contact: Email [email protected] for further information, reference P1144.
This project is to design and build a community pool for Motueka.
You can find more information on this project here: Motueka Pool | Shape Tasman.
| Current status | Planning |
| Start Date | TBC |
| End date | TBC |
| Access | To be advised |
| Contractors | TBC |
| Cost | TBC |
Contact: Email [email protected], reference project 1530.
September 2024 Update:
Stage 2 is 100% complete and the pump station is currently on hold until further developments.
November 2023 Update:
Stage Two: New Wastewater rising main from Pah Street - Motueka Bridge
Stage 2 is over 50% complete. The priority was to complete the construction on State highway 60 before the holiday season.
The team are now working along Parker Street heading towards Atkins Street. 1700m of pipe has been laid out of the proposed 3000m and on track to the programme.
October 2023:
This stage of the project is for the installation of a new polyethylene (PE) wastewater rising main approximately 3 kilometres long. The pipeline alignment will follow Pah Street, Atkins Street, Parker Street, High Street and Lyndhurst Avenue (SH60). All sections can be installed via open trenching methods, with the exception of a short section beneath the Motueka River stopbank which will require use of a trenchless installation technology.
The pipeline will serve the growing communities in Motueka West, conveying wastewater from development there to the wastewater treatment plant.
The pipeline alignment will start at Lyndhurst Avenue SH60 at the Motueka River Bridge and continue along High Street, Parker Street, Atkins Street and Pah Street. All sections of the pipeline will be installed via open trenching.
There are eight phases for this portion of the works. Phase one – between Lyndhurst Ave SH60 to Parker Street turn-off – has now finished.
Beginning in October 2023, work will move along Parker St to the intersection at Te Maatu Drive through to Wilkie Street. From Monday 9 October, the intersection at Te Maatu Drive will be closed so access from High Street into Parker St will only be available for residents in this first section. We expect this stage to take approximately three weeks.
The overall Rising Main project is planned to be completed by May 2024.
We are mindful of the impact that wait times can have on people’s day, and we are aiming to keep these to a minimum.
We thank you in advance for your patience and cooperation during this work.
Stage One: COMPLETE
What are we doing?
To enable growth in this less flood prone and sea level rise affected area, a new pump station and rising main must be installed to deliver wastewater to the wastewater treatment plant (WWTP), pumping via a shared main starting at the Motueka River Bridge.
Why are we doing it?
This project is necessary to serve and enhance any Motueka West developments and incudes the installation of wastewater rider mains along Grey Street from the Green Lane intersection North to Pah Street. The water main will follow the same alignment with an additional branch east along Whakarewa street past Motueka High School.
How will it affect me?
Start Date: 22 August 2022
End Date: January 2023
Contractor: CJ Industries Ltd
Site Contact: Morgan Corrie-Johnston - 021 307 145
Contact: Email [email protected] reference project 1182.
This project is to install a new reservoir to supply High Level Zone at Kaiteriteri above Honeymoon Bay.
|
Current status |
Delivery |
|
Start Date |
2026 (after peak summer season) |
|
End date |
June 2026 |
|
Access |
TBC |
|
Contractors |
Timbertank Enterprises Ltd |
|
Cost |
$94.7k |
Contact: [email protected] for further information, reference 1277.
Update May 2026
Improvements to the Kaiteriteri Water Treatment Plant will help keep the community’s water safe and reliable.
Drinking water for the area comes from two bores on River Road in Riwaka.
The current project builds on an upgrade done in 2018 when UV treatment was added as a protozoa barrier. This upgrade adds to the multi-barrier treatment approach by including additional filtration units, extra pumps and pump housing, and new chlorination systems.
While the plant was originally designed to use chlorination on a temporary, seasonal basis, a decision has since been made to treat all water supplies year-round. To support this, specialist equipment has been installed in response to updated regulations by the water regulator – Taumata Arowai – requiring residual disinfection.
The project has also been designed to deal with occasional water clarity issues. At times, naturally occurring materials in the bore it draws from can cause brief increases in cloudiness. By installing cartridge filters, these particles can be captured before the water reaches the treatment process, improving overall water quality.
In addition, a new automated flush-to-waste system will allow any cloudy water to be safely diverted to the stormwater system in a soak pit instead of flushing water away from the site with hoses into roadside drains.
These upgrades are expected to be completed later this year and will ensure the Kaiteriteri Water Treatment Plant continues to serve the community effectively, now and into the future.
______________________________________________________________________________________
The project is to improve the flush to waste line, filtration and contact tank for the Kaiteriteri Water Treatment Plant. Part of this is to provide extra pumps to suit network pressure requirements and support needs in the community.
|
Current status |
Delivery |
|
Start Date |
July 2025 |
|
End date |
June 2026 |
|
Access |
N/A |
|
Contractors |
Process Flow |
|
Cost |
$981k |
Contact: Email [email protected] for further information, reference 1492.
We’ve chosen the site, so it’s now time to get planning the new community hub for Tapawera.
The hub is earmarked for a site north of Matai Crescent between the Four Square and the skatepark.
It was one of three Council reserve sites that had been considered after due diligence uncovered some challenges with the original community proposal to purchase and demolish the current Tapawera Community Centre.
Reaction to the chosen site has been largely positive.
The next step is to appoint the design team to gather ideas and come up with a preliminary design with guidance from the Tapawera community.
We hope to have a concept plan available early next year, when we’ll ask the community for further input.
All going well, and provided funding targets can be achieved, work on site could begin before the end of next year.
A total of $2.68 million has been allowed for the hub in our 10-Year Plan, with the community required to come up with $900,000 to contribute to the facility, $510,000 of which has already been provided by the Department of Internal Affairs.
Read more updates on Shape Tasman | Tapawera Community Hub.
This project is the development of a new Tapawera Community Hub. It will involve the combining of activities into a new fit for purpose building.
|
Current status |
Planning |
|
Start Date |
TBC |
|
End date |
Aiming for completed facility mid 2027 |
|
Access |
To be advised |
|
Contractors |
Not yet appointed |
|
Cost |
$TBC |
Contact: Email [email protected] for further information, reference 1531.
This project will install two new exterior bores and construct a replacement Water Treatment Plant building to improve the treatment process for water in Tapawera by upgrading systems that work to treat water using UV, chlorine, and filtration.
| Current status | In design and enabling works |
| Start Date | Enabling works Feb 2026 - April 2026 Main construction TBC |
| End date | December 2027 |
| Access | We’ll need some temporary traffic management on Tadmor Valley Road when we reach the construction stages but that should also be minimal. |
| Contractors | Enabling works C1575 - CJ Industries |
| Cost | Enabling works C1575 - $238k Main Contract - $TBC |
The bores will be drilled and developed, then pump tested and sampled over the next five months. Other work will then follow in mid-2025 to install the underground power supply components, before the building and internals are constructed in 2026.
The plant will be commissioned and online by Christmas 2026, then we can decommission the existing plant and bores on the other side of the road.
Having a resilient water supply that continues to meet national drinking water standards is the big driver of the initiative. The new plant will treat the water to a higher standard and be more reliable, but flow and pressure won’t change.
There should be little effect on the water supply during the life of the project, other than some short shutdowns when connecting the plant to the existing network and commissioning.
Contact: Email [email protected] for further information, reference 1494.
This project is to upgrade the Murchison Water Treatment Plant which includes allowing for redundancy for failure and replacement of deteriorated assets. It is one of several Water Treatment Plants we are upgrading in Tasman to provide clean water to local communities.
|
Current status |
Planning/ Design |
|
Start Date |
Construction start July 2026 |
|
End date |
Be completed mid 2027 |
|
Access |
To be advised |
|
Contractors |
Not yet appointed |
|
Cost |
$TBC |
Contact: Email [email protected] for further information, reference 1493.
We are upgrading three different Water Treatment Plant Filtration systems in Golden Bay (Collingwood, Pōhara and Upper Tākaka).
This work includes:
| Current status | Delivery |
| Start Date | Construction early 2025 |
| End date | Construction end May 2026 |
| Access | N/A |
| Contractors | Process Flow |
| Cost | $629K |
Contact: Email [email protected] for further information, reference 1571/ 1491
We have projects set up to look and improve these existing treatment plants to reduce impact on the environment and meet modern standards. In this project we are improving the Secondary Treatment Systems.
| Current status | Delivery |
| Start Date | Feb 2026 |
| End Date | October 2026 |
| Access | N/A |
| Contractors | Mason Engineering NZ Ltd |
| Cost | $2.47m |
Contact: Email [email protected] for further information, reference C1587 / 1451.
Dec 2025 - COMPLETE
Update November 2025
There are changes to Richmond Library opening hours between Monday 17 November and Sunday 30 November as the building gets a new roof.
A major renovation of the Queen Street building has been underway since earlier this year. The $1.3 million upgrade was identified when detailed seismic assessments showed the building needed structural strengthening to improve its earthquake safety.
We’ve also taken the opportunity to tackle some long-standing issues, so the library remains a safe, dry, and welcoming place for everyone.
All that work is largely completed, on time and on budget, so now it’s been decided that while contractors are still on site, we can also get the building re-roofed. This is being paid for from the library’s existing regular maintenance budget.
So, while the work is being done, weekday opening hours will be reduced but we’re extending our weekend hours.
The new hours will be Monday to Friday 5.00 pm until 7.00 pm, then all day Saturday and Sunday from 9.30 am until 4.00 pm. We expect to resume normal opening hours on Monday 1 December.
Any borrowed items which are due during this time can be returned during opening hours or through the Queen Street after-hours returns slot – the Petrie Carpark after-hours returns won’t be available.
To renew your borrowed items, you can call the library on 03 543 8500 or renew them online. The digital library will be available 24/7, and the Wi-Fi will continue to be available outside the building.
Update August 2025
The books are back on the shelves and the doors are open, but the job isn’t quite over yet.
Richmond Library is open again after a month-long closure for strengthening and improvement work, but contractors will be on site for another few months.
The $1.3 million upgrade is needed after a detailed seismic assessment last year showed the building needed structural strengthening to improve its earthquake safety.
Alongside that, we also took the opportunity to tackle some long-standing issues like roof sagging and water tightness, so the library remains a safe, dry, and welcoming place for everyone.
But it hasn’t all been plain sailing.
Once the cladding was off, investigations revealed that the leaking at the Petrie Carpark end of the building was worse than initially thought, so part of that end of the library will remain off limits to users until further repairs are completed.
The July storm couldn’t have come at a worse time for the project either. The rain arrived while the spouting system was being replaced, and unfortunately, one corner had some flooding.
Things are almost back to normal with most of the work now being done on the first floor in the office area, which shouldn’t get in the way of library users.
Despite the additional challenges, the project remains within budget and is to be wrapped up by October as expected.
... And thanks for your patience while this work is being completed.
Update July 2025
Richmond Library is to close for a month while heavy construction work is done during its renovation project.
The $1.3 million upgrade is needed after a detailed seismic assessment last year showed that one part of the building needed structural strengthening to improve its earthquake safety.
Alongside that, we’re taking the opportunity to tackle some long-standing issues like roof sagging and water tightness, so the library remains a safe, dry, and welcoming place for everyone.
Earlier, some Councillors voiced concerns about closing the library for up to four weeks, however after reviewing alternative options, it was decided that a partial opening or a pop-up service during this period would present significant health and safety risks, limit services, and potentially delay the overall programme.
So, the doors will be closed from Saturday 12 July, reopening on Monday 11 August.
But some library services will remain available. Our digital library will still be available 24/7, library Wi-Fi will still be available outside the building, and you can use your Tasman Library card at our Motueka, Tākaka and Murchison libraries.
Tasman residents are also eligible for membership at Nelson City Libraries; you’ll just need to sign up for a Nelson Library card.
Any borrowed items which are due during this time will have their due date adjusted, so you don’t need to worry about getting them back until we reopen on 11 August.
Earthquake strengthening and repairs to the Richmond Library.
|
Current status |
Construction |
|
Start Date |
April 2025 |
|
End date |
December 2025 |
|
Access |
There will be stages of closure which will be notified. |
|
Contractors |
Scott Construction |
|
Cost |
$1.3m |
Contact: Email [email protected] for further information, reference 1593
COMPLETE
We are upgrading three different Water Treatment Plant Filtration systems in Golden Bay (Collingwood, Pōhara and Upper Tākaka).
Works include:
| Current status | Delivery |
| Start Date | Construction Feb 2025 |
| End date | June 2026 |
| Access | N/A |
| Contractors | Process Flow |
| Cost | $309K |
Contact: Email [email protected] for further information, reference 1497/1571.
Project Cancelled
The intersection upgrade on Whakarewa Street in the form of a roundabout near Manoy Street, is to provide safe access to and from the new Whakarewa Phase 1 Housing Development by Wakatu Inc, and the low impact roundabout design needs to cater for the safe egress of cyclists and pedestrians in all four directions.
The timeline for construction will align with provision of other services once design and consenting has progressed further.
Contact: Email [email protected], reference project 1342.
PROJECT COMPLETED OCTOBER 2025
As early as 2008, the Moutere Hills Residents Association workshopped ideas for a footpath to link the village to the community centre and sports ground.
The concept then made it to our list of district-wide footpath projects, but construction couldn’t go ahead until negotiations with landowners were complete and sufficient funding was available.
In October last year, Elected Members met to consider whether we could afford to provide added funding in 2024/2025 for the path, but it was decided this wasn’t possible due to the need to limit increases in rates and debt.
The issue was reconsidered, and the green light was given to bring forward $188,951 of existing budgets from 2025/2026 to 2024/2025 to enable the Upper Moutere shared path to be constructed this year.
The 1300-metre shared concrete and gravel pathway now runs alongside the Moutere Highway, linking the village with the Moutere Hills Community Centre and sports grounds.
More than 60 people took the opportunity to walk and cycle along the new shared path following its official opening and ribbon cutting by Mayor Tim King earlier this month.
This new safe shared walking and cycle path now provides a new travel choice for the community.
We're restarting work on a 1.3 km gravel/concrete shared pathway along the Moutere Highway, connecting the Upper Moutere shops to the Community Hall. This project, initiated by the Moutere Hills Residents Association mhra.org.nz, will provide a safe route for school children and a great option for visitors exploring the area by bike or foot. Thanks to local residents, Upper Moutere School, and the Moutere Hills Community Centre for their support.
Update October 2025
Project has progressed extremely well and due to finish works first week of November 2025. Most of the pathway is complete except for the main village section, once the concrete path is laid, the path will be opened for use.
Update June 2025
Project is well underway and estimated 30% completion. Project has been delayed due to wet ground conditions and weather disruptions. Estimated due to be completed now in September 2025.
· Stage 1 – 1475 Upper Moutere Road to fire station, Start: Thursday, 19 June 2025
· Stage 2 – Fire Station to the upper Moutere Dairy, Start: Friday, 18 July 2025
· Stage 3 – 11 Keeling Road to Community Hall, Start: Thursday, 4 September 2025
View the map below or or open it in a new tab for larger version.
Update December 2024
Project on Hold: The Upper Moutere shared path has faced multiple delays since it was first proposed by the Moutere Hills Residents Association in 2008. The project stalled in 2021 due to unresolved landowner negotiations but was revived earlier this year. However, funding challenges arose when NZTA Waka Kotahi declined government funding for the project in September 2024, leaving Council to reconsider its options. On 24 October 2024, elected members decided against providing additional funding for 2024/25 to avoid rate and debt increases. The path is now set for completion in 2025/26, funded entirely by the Council over two years.
|
Current Status: |
Delivery |
|
Start Date: |
March 2025 |
|
End Date: |
Sept 2025 |
|
Access: |
The road will remain open and access will aways be given to affected residents. |
|
Contractor/s: |
Wenham Contracting |
|
Cost: |
$400,000 |
Contact: Email [email protected] reference 1557.
Map
Below is a map of the route of the pathway.
Upper Moutere Shared Pathway Route
View the full PDF version:
We’re making improvements at an old trouble spot in our Richmond stormwater network.
Easby Park is located between Marlborough Crescent and Selbourne Avenue and has had a technical makeover to improve the way its drainage system copes with increased water flow during wet weather.
The work included building an extra area within the park with a secondary intake into the piped section of Reservoir Creek for when the existing primary intake is blocked.
We’ve also increased the capacity of roadside sumps in Selbourne Avenue and Polglase Street.
In other work, we’ve redesigned and modified the primary inlet structure so that it is less prone to blocking, and to make it safer and easier for contractors to clear debris.
In the future, we’ll be looking into an extra debris screen further upstream in Easby Park, which will minimise the frequency of blocking and provide additional capacity downstream.
This project is to reduce the effects of overland flow path that runs through Easby Park and onto Selbourne Ave. This will in tale some stormwater structures being installed in Easby Park.
|
Current status |
Delivery |
|
Start Date |
Construction Start: The work is scheduled to start mid August and will take about 3-4 weeks to complete. |
|
End date |
Construction End: Sept/Oct 2025 |
|
Access |
While work is underway, you may notice daytime construction noise. Public access through Easby Park will always remain open. However, access will be narrower than usual between Selbourne Avenue and Marlborough Crescent, so please take care when walking or cycling through this section. |
|
Contractors |
CJ Industries |
|
Cost |
$105.8k |
Contact: Email [email protected] for more information, reference 1578.
COMPLETE
We are upgrading three different Water Treatment Plant Filtration systems in Golden Bay (Collingwood, Pōhara and Upper Tākaka).
Works include:
| Current status | Complete |
| Start Date | Construction 2025 |
| End date | Construction end June 2026 |
| Access | N/A |
| Contractors | Process Flow |
| Cost | $103K |
Contact: Email [email protected] for further information, reference 1498, 1587.
COMPLETED
This project is part of the upgrade being undertaken at Port Tarakohe Programme of work. This piece of construction is of an office and amenities block with a specialised marine waste management system.
|
Status |
Complete |
|
Start Date: |
October 2024 |
|
End Date: |
August 2025 |
|
Contractor/s: |
Coman Construction |
|
Cost: |
$1.6m |
Contact [email protected] for further information, reference 1424.
Why are we doing it?
This facility is designed to provide space for people who work in the commercial operations to work here and be a space for effective work and improve growth of this Port Tarakohe. It will also enable the users of the port to have new hygiene facilities and provide an office for the Tasman District Council staff to conduct their business.
The design
The concept design integrates both design influences from Māori lookout posts, Golden Bay cement history as well as embracing new technologies for a low-carbon and sustainable office design build. This office includes a room for commercial operators and amenities.
Office and Amenities Block Drawing Design
COMPLETED
This project to increase Levels of Service and reduce flooding along the west side of High Street and around the Wratt Street / Woodlands Ave intersection.
Kicking off mid 2024, we have started by investigating the work, this will be developed in two more (since the Motueka West Stormwater Discharge System project) stages and be totally complete in 2027.
| Current status | Complete |
| Start Date | Works underway start of 2025 |
| End date | Construction end mid 2025 |
| Access | 17th March 2025 Woodlands Ave will be closed between the intersections of Wratt Street and Lowe Street to allow for Stormwater installation works. Traffic passing through Woodlands Ave will be detoured via State Highway 60. Residents within the closure (Woodlands Ave between Wratt Street and Lowe Street) will be able to enter and exit Woodlands Ave via the Woodlands/Lowe Street intersection (Northen end of Woodlands Ave) |
| Contractors | Stage 2 – Fulton Hogan, Stage 3 - TBC |
| Cost | $588K |
Wratt Street Overland flow path investigations at Woodlands Ave - Ground Penetrating Radar, potholing and coal tar sampling.
Contact:
Email [email protected] for further information, reference Project 1503.
COMPLETED
We are building a combined new right of way for residents and an infrastructure maintenance road. This project is part of enabling the wider stormwater improvement work for Richmond South.
|
Current status |
Complete |
|
Start Date |
Mid Feb 2025 |
|
End date |
August 2025 |
|
Access |
Shoulder will be closed through March and April, which means traffic will still be able to go through most of the time, with a day or two having stop/go for trenching across the road. |
|
Contractors |
Mike Edridge Contracting |
|
Cost |
$500,000 |
Contact: Email [email protected] for further information, reference 1570.
Last modified: